C L E A R .  C O N T R O L L E D .  D E L I V E R E D .

Menu
  • Portfolio
  • Team
  • Insights
  • Join Us | Vision & Mission
  • Contact
  • Data & Digital
  • Project Planning & Controls
  • Project & Commercial Management
Contact Us

C L E A R . C O N T R O L L E D . D E L I V E R E D .

  • Data & Digital
  • Project Planning & Controls
  • Project & Commercial Management
  • Portfolio
  • Insights
  • Team
  • Join Us | Vision & Mission
Menu
  • Data & Digital
  • Project Planning & Controls
  • Project & Commercial Management
  • Portfolio
  • Insights
  • Team
  • Join Us | Vision & Mission
Contact Us
Portfolio & Case Studies

We combine our engineering and
construction experience with our digital
skills to make solutions that drive decision
making at all levels of the project team.

  • footer_arrow Clear.
  • footer_arrow Controlled.
  • footer_arrow Delivered.
We delivered a detailed contract programme and proactive delay claims for a £20m mechanical and electrical installation under and NEC3 contract

Interested in how we can help your team?

Email us
We delivered a detailed contract programme and proactive delay claims for a £20m mechanical and electrical installation under and NEC3 contract

Northern Line Extension

The extension of the Northern line to the Vauxhall, Nine Elms and Battersea areas. Our client was contracted to deliver M&E fit out works under an NEC3 Fixed Cost contract.

The Challenges

  1. The project experienced significant delays due to design changes and access issues which were mostly due to client change. These delays directly impacted the planned completion of the project and therefore needed to be claimed as compensation events.
  2. A high level of complexity on the project but with a small team to deliver meant that it was difficult to keep a clear understanding of what was going on and what needed to be done when.

Our Solution

Programme Management

The programme was broken down into the lowest level of detail required to demonstrate delay. This was every work area where there may be design or access issues. We ensured client dependencies and blockers were clearly defined on the Programme for acceptance with the critical path clearly defined and client delay explained in programme narrative.

This allowed us to clearly communicate the knock on effects of the client delays to the rest of the project so that they understood the basis of the compensation events.

Data Analytics

We deployed an extensive Power BI analytics app that gave the project team access to their programme data, earned value, blockers lists, contractual communications and more. It toed the data sets together to provide the project manager with a kind of command center that allowed him to see what the key areas were that he should focus on.

Key Outcomes

  • Proactive extension of the contract completion date and an increase to the contract value to cover preliminaries over the extended period.
  • Clarity for the project team on key tasks and issues by putting hidden or difficult to access data at their fingertips.

Final Thoughts

When it is clearly shown on the programme there is no argument when it comes to compensation events. This allows an easy agreement with the client as well as water tight evidence if things evolve into an adjudication scenario.

PrevPrevious
NextNext
title_arrows_blue

More Case Studies

hs2

HS2 Main Works C2-C3

A major contractor needed assistance with data management and reporting improvements. We established a roadmap and then delivered rolling upgrades to their systems.

Read More »

Series of Hyperscale Data Centres

Integration of complex systems, design changes, fast build time. Optimum planning & project controls is key for the success of the construction of these £500m giants.

Read More »

Full Programme Management Function for SME Contractor

We provided a full project planning & controls department for a medium sized contractor with £45m turnover

Read More »
  • footer_arrow Portfolio
  • footer_arrow Insight
  • footer_arrow Team
  • footer_arrow Join Us | Vision & Mission
  • footer_arrow Data & Digital
  • footer_arrow Project Planning & Controls
  • footer_arrow Project & Commercial Management
Contact Us

© All rights reserved Laminar 2022 Laminar Group Ltd. Registration No.11108678 Registered Office: 20-22 Wenlock Road London N1 7GU United Kingdom. Place of Registration – England & Wales. VAT No. 291810402.

Privacy Policy

  • footer_arrow Portfolio
  • footer_arrow Insight
  • footer_arrow Team
  • footer_arrow Join Us
  • footer_arrow Data & Digital
  • footer_arrow Project Planning & Controls
  • footer_arrow Project & Commercial Management
Contact Us

© All rights reserved Laminar 2019 Laminar Group Ltd. Registration No.11108678 Registered Office: 20-22 Wenlock Road London N1 7GU United Kingdom. Place of Registration – England & Wales. VAT No. 291810402.

Privacy Policy

Go to mobile version