C L E A R .  C O N T R O L L E D .  D E L I V E R E D .

Menu
  • Portfolio
  • Team
  • Insights
  • Join Us | Vision & Mission
  • Contact
  • Data & Digital
  • Project Planning & Controls
  • Project & Commercial Management
Contact Us

C L E A R . C O N T R O L L E D . D E L I V E R E D .

  • Data & Digital
  • Project Planning & Controls
  • Project & Commercial Management
  • Portfolio
  • Insights
  • Team
  • Join Us | Vision & Mission
Menu
  • Data & Digital
  • Project Planning & Controls
  • Project & Commercial Management
  • Portfolio
  • Insights
  • Team
  • Join Us | Vision & Mission
Contact Us
Insights

Articles by our team on optimising your project performance with best practice, technology and a bit of common sense!

  • footer_arrow Clear.
  • footer_arrow Controlled.
  • footer_arrow Delivered.
constructing datacentres
Insights
Neglecting these elements leaves the contractor commercially vulnerable to client delays due to the lack of evidence that the third party dependency was the real cause of change.

3 Fundamentals to Ensure a Commercially Robust NEC3 Programme

There are many of things to consider when developing an NEC3 compliant programme. But here I want to focus on three fundamentals that are constantly overlooked by main contractors and sub-contractors in their programme development.

Neglecting these elements leaves the contractor commercially vulnerable to client delays due to the lack of evidence that the third party dependency was the real cause of change.

1) Maintaining the Terminal Float

The time between the contractual Completion Date and the planned Completion is commonly referred to as the terminal float (not a defined term). It is clearly stated in the contract that this float is owned by the contractor which means that any delay caused by the client cannot be mitigated by using up the terminal float.

What this means in practice is that if the client causes delays to the planned Completion, the Completion Date will move by the same amount once a compensation event is implemented.

The very same principle also applies to Key Dates and Sectional Completion.

2) Clearly Show Key Dates

Key Dates are defined in the contract as dates for achieving an intermediate milestone. The purpose of key dates is to allow the client to coordinate works between project interfaces and to assign delay damages for not achieving them.

These dates are treated in a similar way to Sectional Completion dates and should have both a planned and contractual date shown in the programme along with the terminal float.

I have frequently seen programmes missing key dates or having progress monitoring milestones labelled as Key Dates when they are not.

3) Client / Third Party dependencies

Without a doubt, the most important information to show on a contract programme are the client and third-party dependencies. These are things that the contractor has no control over but is dependent on to do the works. Demonstration of how any delays affect the planned Completion will form the basis of a Compensation event so it is critical that they are fully logic linked to the activities that depend on them.

The main liability that a client takes on when accepting a programme is that they will provide their deliverables by the dates stated in the Accepted Programme. A simple method to make it easier for the client to accept the programme is to include a filter of client deliverables along with the programme submission.

Final Thoughts

This is just a quick overview of the main things to keep an eye on commercially when developing and maintaining a programme under an NEC contract. Despite being critically important, these principles are often overlooked by project teams resulting in lost opportunities to recover costs from the client and decimating margins.

NextNext

More Insights

Construction projects can be drama free and run like clockwork

A construction project going wrong is no surprise to anyone. It’s so common from systematic delays to budget overruns that even people who don’t work in this sector know it.

Read More »

3 things the perfect Project Leader does

Let’s face it, there’s no such thing as a Perfect Project Leader, but some are pretty close. A good project leader does a lot of things but these are 3 things all perfect ones do.

Read More »

Construction Cowboys: “Hi-yo, Silver! Away!”

We construction people all have a little bit of construction cowboy in us. It’s that restlessness you get when stuff isn’t getting done, those cold sweats when it has been too long since your last concrete pour, the little feeling of pride as you did your hard hat to get out and build a monument to humanity’s greatness.

Read More »
  • footer_arrow Portfolio
  • footer_arrow Insight
  • footer_arrow Team
  • footer_arrow Join Us | Vision & Mission
  • footer_arrow Data & Digital
  • footer_arrow Project Planning & Controls
  • footer_arrow Project & Commercial Management
Contact Us

© All rights reserved Laminar 2022 Laminar Group Ltd. Registration No.11108678 Registered Office: 20-22 Wenlock Road London N1 7GU United Kingdom. Place of Registration – England & Wales. VAT No. 291810402.

Privacy Policy

  • footer_arrow Portfolio
  • footer_arrow Insight
  • footer_arrow Team
  • footer_arrow Join Us
  • footer_arrow Data & Digital
  • footer_arrow Project Planning & Controls
  • footer_arrow Project & Commercial Management
Contact Us

© All rights reserved Laminar 2019 Laminar Group Ltd. Registration No.11108678 Registered Office: 20-22 Wenlock Road London N1 7GU United Kingdom. Place of Registration – England & Wales. VAT No. 291810402.

Privacy Policy

Go to mobile version